January 11th  update

 

Visually it was one of the most exciting weeks of the new  year.
This week the wallboard was hung throughout the house closing in
walls that had been open for months.

With the wallboard team working our
 crew got a bit of a break (we let them eat lunch), but progress continued wherever
 they could work that was out of the way.

The final insulation was put into ceilings downstairs as the wallboard was
 hung in the attic.
 

The fireplace in the Living
Room was prepared for its
wallboard facing.

 With the wallboard being hung in the
next room,  Jim quickly installed
an electric box for a last minute
additional light for a closet.
 

Meanwhile our crew constructed a screen
for the exterior HVAC and worked on
the double rear dormer.

On Friday it was beginning to look
like the interior of a gracious home
once again. Next week - a lot
of wallboard seams to tape and "mud".

May 10

May 16

May 22

May 31 June 5

June 7

June 14

June 20

July 10

July 19

July 24

August 1

August 15

August 22

August 29

September 5

September 14

September 21

September 27

October 3

October 25

November 1

November 10

November 16

November 21

November 30

December 7

December 15

December 28

 Jan. 4

Jan. 11

Jan. 18

Jan. 26

Feb. 1

Feb. 10

Feb. 15

Feb. 29

March 7

March 14

March 29

April 4

April 11

April 18

April 25

May 3, 2008

May 9, 2008

 

Home

The Manse

Manse History

Renovation Plans

Fund Raising Needs

How to Donate

Volunteers in Action

Presbyterian Church on Edisto Is.

Church Mission

Sanctuary Renovation

To read memories from Dr. Charles Spencer of  "An Idyllic Childhood in the Old Manse"
 Click Here

To read memories from Dr. Charles Spencer of  "How the Manse Survived Three Fires"
Click Here